BioPharmaceutical Client

PROJECT BRIEF

BREFFNI AIR were awarded this landmark contract in 2016 by the fifth largest construction company in the world, with works commencing onsite in March 2017.

As the main ducting subcontractor on this impressive facility, all ducting was manufactured in Cavan Ireland, shipped and installed by Breffni Air onsite.

Approximately 40% of the works called for BS EN12101-7 Fire Rated Ductwork standard and also kitchen extract to EN 15871 standard, again manufactured and expertly installed and certified by Breffni Air.

Galvanised Supply and Return Ductwork formed the remainder of this 18 month project with installations in Basement, Process, Laboratories, Packaging and Administration areas.

CONTRACT

New Pharmaceutical Building Cambridge

COMMENCEMENT

March 2017

COMPLETION

TBC

REQUIREMENT

52,000 m2 of new duct